Optus Stadium Turf
Department
Civil
Client
HG Sports Turf
Time
Jan 2017 to Jul 2017
Value
Approx $1,000,000
Team
Michael Collins
Scope of Works
- Earthworks
- Subsoil Drainage
- Import Subbase Filter Rock Layer
- Import and Trim Root Zone Sand Layer
Project Features
- All import through Confined Access Points
- Low Ground Pressure machines with Custom Buckets moved 8,000m3 of Material